Important Milestone reached

The assembly of the heavy parts at ROMONTA site is nearly completed.

June 2023

 

We are pleased to announce that we have reached another significant milestone on site DK7! After an intensive 4 weeks, we have successfully completed the assembly of the heavy parts and positioned the drum. The complete boiler is aligned but not yet completely welded.

In addition to the welding work on the boiler, we started installing the downcomers and the connecting tubes to the steam drum in the following week, followed by the piping. In parallel, the assembly of the air ducts and completion of the components in the boiler house is underway. 

In the compressed air room, exhaust air ducts and equipment for the compressed air system are already being installed, and in the electrical rooms the raised floor is being laid on site.
On the foundation plate of the RGR, the steel construction assembly begins, supplemented by the first components of the flue gas cleaning system. The following week, the assembly of the crane runways in the slag and fuel bunker begins.

Despite some challenges, we can be proud of the smooth progress of the overall execution. We have proven that we can stick together even in difficult situations and find solutions together.

A big thank you to everyone involved for their tireless efforts and valuable cooperation. Only in a functioning team can the tasks set be mastered.

Technical Data

Rated Thermal Input (RTI)

55 MW

Steam Parameter

Steam Capacity63,5 t/h

Steam Temperature422 °C

Steam Pressure77 bar

Construction of Steel Structure

You are looking for current information from the field of plant engineering and energy generation? Would you like to find out about upcoming exhibitions and other dates?

You can also get more news via our social media channels:

Standardkessel Baumgarte on LinkedIn
Standardkessel Baumgarte on Xing