While we were officially able to announce our new order a few weeks ago, visible progress has already been made on the project in the meantime.
Together, our construction site team at the Schwarze Pumpe Industrial Park was able to place the first of the large boiler columns for the new RDF power plant This event marks the transition from the planning to the construction phase and symbolises the successful start of the project for us as plant engineers.
Special thanks go to our team led by Dr Peter Marek, who are doing a great job in close coordination with our customer The trusting dialogue and committed collaboration have made this successful start possible We look forward to the next stages and wish the entire team and our customer continued successful and good cooperation.
The next milestone will be the start of heavy component assembly.
Technical Data
nom.80 MW
nom.101,5 t/h
40 bar
400 °C
Impressions from the Construction Site