The building work for the construction of the heat recovery plant in Flensburg is on schedule. Ten weeks after the first boiler support beam was set in place, in November the boiler modules as well as the HP and LP drums were inserted. Hence the whole basic body of the boiler has been lifted into the steel structure.

 

In the next step the ducts and, from January 2015, the piping will be fitted so that on 5 February 2015 a punctual start can probably be made on the hot commissioning of the gas turbine.