SBG lights first Fire in Dundee

March 2021

MVV Environment Baldovie Ltd awarded SBG with the contract as general contractor for the construction of the new Energy from Waste (EfW) plant, which shall replace an old fluidised bed combustion plant in the future. SBG relied on the proven air-cooled SBG pusher-type grate for the firing system.

 

Ignition of the first fire

 

On Tuesday, 16.03.2021, the grate firing system was successfully ignited for the first time using household waste. We would like to thank the entire team and look forward to the remaining commissioning work with confidence, despite the currently difficult Corona situation.
 

Technical Data

Rated Thermal Input                  39,9 MWth
Fuel Throughput Rate (nom.)    13,72 t/h
Steam Capacity                          49,1 t/h
Steam Temperature                   405 °C
Steam Pressure                          43 bar (g)

 

More technical information can be found here:

https://www.standardkessel-baumgarte.com/uploads/tx_download/REFERENCE_SHEET_DUNDEE.pdf

 

News Download:

PDF-Download (1 MB)

PDF herunterladen

You are looking for current information from the field of plant engineering and energy generation? Would you like to find out about upcoming exhibitions and other dates?

You can also get more news via our social media channels:

Standardkessel Baumgarte on LinkedIn
Standardkessel Baumgarte on Xing