November 2019

On 20.11.2019, the official boiler pressure test on incineration line No. 2 in Karlsruhe Sewage Treatment Plant was successfully completed. The boiler withstood the pressure test at a test pressure of 84.5 bar (gauge).

 

Hence, an important milestone was reached on the way to successful completion of incineration line No. 2 in the sewage treatment plant.

 

Within the scope of modernization work in incineration line No. 2, in June 2019 Standardkessel Baumgarte was entrusted with the completion and commissioning of the line.