Successful pressure test in the waste incineration plant Bremen

August 2012

The pressure test on boiler 4 in the waste incineration plant was successfully completed eight weeks ahead of the contractually agreed deadline.

 

On August 1, 2012 a heating surface of about 7625 m² proved its tightness at a boiler pressure of 115.5 bar. 

 

In June 2010 Baumgarte Boiler Systems was given the order to modernize the existing power plant MHKW Bremen. After converting the saturated steam boiler to a superheated steam generator and the successfully performed pressure test in June 2011, the construction of boiler 4 got underway. 

 

Boiler 1 started its operation in December 2011. As of December 2012 the boilers identical in construction shall both ensure the supply of heat and power to the City of Bremen

You are looking for current information from the field of plant engineering and energy generation? Would you like to find out about upcoming exhibitions and other dates?

You can also get more news via our social media channels:

Standardkessel Baumgarte on LinkedIn
Standardkessel Baumgarte on Xing