1st steel support installed on the Scholven construction site

June 2020

On 05.06.2020 the first boiler support was installed at the Gelsenkirchen-Scholven refinery location for the two future steam generating plants. The first important milestone has thus been reached.

 

In the next step, first the complete steel supporting structure will be hoisted into place and the fresh air and flue gas ducts installed. After that, the components will be positioned on the different levels and, parallel to that, the combustion chamber will be pre-assembled and lifted into place. Subsequently, the assembly work will start on the next of the total of four steam generators.

 

The new steam generating plants are part of a comprehensive modernization project that STEAG GmbH is implementing for Ruhr Oel GmbH at the refinery location in Gelsenkirchen-Scholven. Standardkessel Baumgarte GmbH is supplying the energy-efficient steam generators.

You are looking for current information from the field of plant engineering and energy generation? Would you like to find out about upcoming exhibitions and other dates?

You can also get more news via our social media channels:

Standardkessel Baumgarte on LinkedIn
Standardkessel Baumgarte on Xing