January 2023
In 2022, SBG, as a subsidiary of JFE Engineering, received the order to take over parts of the plant engineering, especially in the realization of the furnace and steam generator.
Now the boiler drum was successfully lifted in and placed in the steel structure. In a further assembly step, the drum is then welded to the pressure part.
The new WtE plant is designed to incinerate 500 tons of domestic and industrial waste per day and is expected to generate up to 91,872 MWh of electricity annually. In the future, the electrical energy produced will be supplied to the Vietnam Electricity Corporation under a feed-in tariff system.
Drum lifting at Bac Ninh site