Indaver, European player in sustainable waste management sector, and SUEZ, world leader in smart and sustainable resource management, will construct and operate a new biomass power plant in Beveren (Belgium), via their joint-venture E-Wood Energiecentrale NV.
Standardkessel Baumgarte GmbH has been awarded the contract for the supply, construction and commissioning of the entire power plant as the general contractor.

 

The new E-Wood biomass power plant is to utilize approx. 180,000 tons of non-recyclable used wood per annum. As the firing system, a stationary fluidized bed will be used which provides decisive advantages regarding the emission limit values to be complied with.
The power plant will have an electrical power of 20 MWel and will additionally produce high-pressure steam which will be injected into the ECLUSE steam network in the Waasland Port.

 

The future biomass power plant will be located near the Antwerp container terminal, where the joint owners, SUEZ and Indaver, already operate three waste incineration lines whose steam generators were supplied in 2006, also by Standardkessel Baumgarte.

 

Technical Data:
Rated thermal input: 71 MWth
Electrical power: 20 MWel
Export steam quantity: 10 t/h

You are looking for current information from the field of plant engineering and energy generation? Would you like to find out about upcoming exhibitions and other dates?

You can also get more news via our social media channels:

Standardkessel Baumgarte on LinkedIn
Standardkessel Baumgarte on Xing