The Task
Romonta EBS GmbH plans to further expand the waste utilisation centre for a capacity of 240,000 t/a RDF and to discontinue the previous energy recovery of the residual coal produced in the company's own power plant by 2024. To ensure the necessary heat supply for the site, a new steam generation plant with RDF firing is to be built. Standardkessel Baumgarte was commissioned with the construction of the RDF power plant. Romonta and Standardkessel Baumgarte have already worked together successfully on the construction of RDF boiler plants in 2004 and 2009.
The Solution
The plant is designed with the already proven Standardkessel Baumgarte firing and boiler concept. The core of the plant is a water-cooled moving grate and a steam generator in tail-end design. The flue gases are cleaned in a downstream flue gas cleaning system that operates according to the dry adsorption principle.
For more information, please see our reference sheet.
"We deliver an innovative and specially adapted technology for a sustainable and effective energy supply tailor-made for your needs".
Olaf Schumacher
Head of Sales
Technical data
1
Refuse Derived Fuel, Municipal Solid Waste
min.8.0 MJ/kg
nom.13.0 MJ/kg
max.18.0 MJ/kg
Minimal10.66 t/h
nom.15.23 t/h
Maximal18.0 t/h
55 MW
64 t/h
77 bar
422 °C
103 °C
(wet)108,790 Nm³/h
140 °C
17. BImSchV
2024