Energy from Waste Power Plant

Chalampé, 
France

The task

The natural gas operated power plant park of ALSACHIMIE (a BASF and Domo Chemicals company) at the industrial site
F-Chalampé, which has existed for decades, will be supplemented by the EPCC (Energy Production Centre Chalampé) of B+T Energie France S.A.S..

Standardkessel Baumgarte, as general contractor, will supply the entire plant and process engineering of the EPCC, which will contribute to the base load supply of high and low pressure steam for the production facilities of ALSACHIMIE. The energy will be generated on the basis of regional refuse derived fuel, commercial waste and other solid waste fuels to replace the fuel natural gas used so far in these quantities.

The solution

A 2-lane air/water-cooled grate takes over the safe combustion of the residual materials. The downstream boiler in multi-pass design with horizontal tailend and external economizer takes over the generation of the required steam quantities. The further scope of supply of Standardkessel Baumgarte also includes the flue gas treatment plant which operates according to the "Conditioned Dry-Sorption Process" on the basis of hydrated lime / activated carbon and is classified as a semi-dry FGT system. A small back-pressure steam turbine generator set generates the required electrical power for the plant.

For more information, please see our reference sheet.

Fuel

Refuse derived fuels, commercial waste and other solid waste fuels

Number of Lines

1

Low Heating Value

16.0
MJ/kg maximal
 

Fuel Throughput

12.8
t/h

Rated Thermal Input

80
MW

Steam Capacity

96.8
t/h

Steam Temperature

425
°C 

Steam Pressure

66
bar

Feed Water Tempterature

130
°C

Flue Gas Flow

147,000
Nm³/h nominal

Flue Gas Temperature Exit

160
°C

Commissioning

2023
Q4

Emission Values

BREF

“We deliver an innovative and specially adapted technology for a sustainable and effective energy supply tailor-made for your needs.”

Olaf Schumacher
Head of Sales

Read these articles too

Here you will find further news articles on the project – an overview of all previous articles, allowing you to follow the progress and development in detail.

Energy from Waste Power Plant Chalampé, France

Steam Capacity: 96,8 t/h 

August 2023

Successful commissioning in Chalampé

July 2023

Preparations for the ‘first fire’ with substitute fuel in Chalampé

June 2023

Successful boiler pressure test for the Protos project

October 2022

Pressure test Chalampé: Our weld seams are also tight in France