Biomass Power Plant

Elsterwerda,
Germany

The task

On the area of an existing district heating plant, owned by Stadtwerke Elsterwerda, a new biomass plant should be installed. The new biomass power plant should replace the old district heating plant and additionally produce electrical power for the public grid.

Biomass is used as fuel, according to the definition of the German
“Biomass Legislation”.

The order was placed to Standardkessel Baumgarte in November 2001.

The solution

The plant is equipped with the following procedural units. The fuel is delivered by trucks. Beginning with the receiving station the fuel is conveyed into the storage silos. From there the fuel arrives in the boiler area via a conveying system.

The thermal part consists of grate firing system, steam generator and flue gas cleaning.

The electrical energy being generated in the turbine/generator is fed into the public grid and the process steam into the steam net of the heating power station.

The back up for the district heating system is done by an auxiliary boiler.

For more information, please see our reference sheet.

Fuel

Waste Wood (A1-A2), Lightoil, Natural Gas

Low Heating Value

10.0
MJ/kg minimal

13.4
MJ/kg nominal

16.0
MJ/kg maximal
 

Fuel Flow

12.2
t/h nominal

Rated Thermal Input

44
MW

Electrical Output ST

12
MW

District Heating

12 
MW

Steam Flow

50
t/h

Steam Temperature

452
°C 

Steam Pressure

66
bar

Feed Water Temperasture

105
°C

Flue Gas Temperature Exit

180
°C

Commissioning

2004

Operating Permit

17. BImSchV

Flue Gas Flow

102,000
nominal m³/h i.N.

Boiler Type

Natural Circulation

Ideas full of energy!

“Thanks to our broad product portfolio in the field of biomass firing systems, we can always offer our customers an optimal solution.”

Olaf Schumacher
Head of Sales